Workers on scaffolding install gutters and shingles on the roof of a stone building surrounded by trees.

A First-Timer’s Guide to Gutter Replacement

Replacing gutters for the first time comes down to a few questions in order: is the run worth saving, how much water has to move, and what the bid should spell out. Then check the finished job.

Licensing, permit, lien and tax rules vary by state and city and change over time. This guide is general information, not legal or tax advice; check with your local building department, state licensing board or a professional for your situation.

Checklist

  • Most U.S. homes use 5-inch K-style or 6-inch half-round gutters, and steep or complicated roofs may need more capacity or more downspouts.
  • Sizing starts with the drainage area feeding each run, adjusted for roof pitch, then compared against local rainfall intensity in inches per hour.
  • Each square inch of downspout cross section drains about 100 square feet of watershed, so a 2-by-3-inch spout handles up to 600 square feet.
  • Aluminum coil comes in .027 and .032 inch stocks, and the thicker one resists denting and sagging on long runs, ice, and two-story walls.
  • A bid should name the profile, coil thickness in decimal inches, downspout count and discharge points, and hanger type and spacing.

Gutters are one of the few exterior systems a homeowner can judge from the ground, which is why a bad replacement shows up fast. Water sheets over the front lip, stains the siding, and pools near the foundation. This guide walks through the decisions in the order they arrive: repair or replace, how the system gets sized, what a bid should say, and what to check before the crew leaves.

Repair or Replace: How to Tell Which You Need

A single problem on an otherwise sound run is usually a repair. One sagging section, a pulled hanger, a leaking corner, or a joint that opens on a sectional run can be fixed without tearing off the whole system.

Replace when failures are spread out. Look for splits and holes along several sections, rust-through on steel, paint peeling in sheets, or water that spills over the front in a steady rain. Check the fascia, the board the gutter fastens to. If it is soft when you push a screwdriver into it, the gutter was loose for a while, and new metal on rotten wood will pull free again.

Trade sources put the working life of aluminum gutters at 20 years or more, so an original run that is failing in several places is usually past patching.

Sizing Gutters and Downspouts to Your Roof Area

Most homes use 5-inch K-style gutters or 6-inch half-round. What matters is whether the size matches the water arriving at the eave.

Start with the drainage area, the roof surface feeding one stretch of gutter. On a simple gable roof that means two planes. Valleys, where roof planes meet, dump a large volume at one point, so those runs need extra capacity or another downspout.

Pitch changes how fast water arrives. A steep roof sheds quickly and catches more wind-driven rain, and sizing tables apply a pitch factor to the roof’s surface area: 1.1 for an 8-in-12 roof.

Rainfall intensity is the other input, measured in inches per hour during the heaviest short burst a region is likely to see. The SMACNA sizing tables use a 5-minute duration for a 10-year or 100-year storm, and the National Oceanic and Atmospheric Administration keeps updating the rainfall data behind them.

A published example shows how the numbers combine. A 40-foot-wide shed roof with a 20-foot rafter covers 800 square feet. The 8-in-12 pitch factor of 1.1 brings the watershed to 880 square feet. A 5-inch K-style gutter is rated for a 5,520-square-foot watershed at 1 inch of rain per hour; divide by Washington’s 6.6 inches per hour and the limit is 836 square feet. That run is slightly over, so the fix is a second downspout, a larger gutter, or the pitch allowance: slope the gutter 1/8 inch per foot and you can multiply the watershed by 1.4.

Downspouts follow a simpler rule. Each square inch of spout cross section drains 100 square feet of watershed.

Downspout size Cross section Watershed one spout can drain
2 by 3 in. 6 sq. in. Up to 600 sq. ft.
3 by 4 in. 12 sq. in. Up to 1,200 sq. ft.

That is why adding a second downspout matters: two spouts double what a stretch of gutter can handle. The International Plumbing Code was also updated in 2015 with revised storm drainage sizing for gutters and downspouts, and some jurisdictions size to it.

Site-Formed vs. Sectional Gutters and What Gauge Means

Gutters arrive as pieces or as coil. A site-formed gutter starts as flat painted aluminum on a truck, gets pressed into a K-style profile by a roll-forming machine, and is cut to the length of your run, so joints appear only at corners and outlets. Sectional gutters come in fixed lengths and are joined with seams, and those seams are where drips tend to start after some years.

Thickness is where bids get vague. Aluminum coil is measured in thousandths of an inch, and the two residential stocks are .027 and .032. Contractors often say gauge, which is common usage but the wrong term for aluminum, since gauge systems apply to steel. Both stocks are the same alloy family, take the same factory paint, and form the same 5-inch or 6-inch profile.

The difference is small on paper and noticeable on a house. Moving from .027 to .032 adds about 18 percent more aluminum and roughly 50 percent more resistance to bending and denting. The front lip, where ladders land, springs back instead of creasing. Long runs hold a straighter line between hangers. On two-story elevations, steep roofs, and anywhere ice sits in the trough, .032 is worth paying for. A .040 coil is commercial grade, usually more than a house needs.

None of that fixes a hanger or pitch problem. A thick gutter spaced too far apart still waves, and one sloping the wrong way still holds water. Aluminum moves with temperature more than most roofing metals, so long runs need room to slide, and it should never touch copper.

What a Gutter Bid Should Include

Ask for a written proposal listing the profile and size, the coil thickness in decimal inches, the linear footage, the number and size of downspouts, hanger type and spacing, corners, end caps, and outlets. Removal and disposal of the old material belongs on the page, along with any fascia repair the crew expects. Color should be a manufacturer name or number, not brown.

Have the bid state whether hangers are hidden or spikes and ferrules, and what happens if the fascia turns out to be soft. What a home improvement contract should say covers the clauses that matter when a job changes midstream.

Tip

Ask each bidder to state the downspout count and where each one discharges. Two bids for the same footage can differ by two or three downspouts, and that changes how the finished system works.

Questions to Ask Before You Sign

Who sized the system, and can they show the calculation? A crew that measures footage and picks 5-inch stock by habit is guessing.

Will the crew replace rotten fascia, or hang new gutter over it? What is the hanger spacing?

Where does each downspout discharge, and is that far enough from the foundation?

Who is on the crew, and does the company carry liability insurance and workers’ compensation? Ask for certificates.

What does the warranty cover, labor or materials, and for how long?

The steps in how to hire a roofing contractor apply almost word for word here, since gutter work sits on the same eave and often rides along with a roof job.

Permits, HOA Rules and Drainage Rules to Check First

Whether a gutter replacement needs a permit depends on where you live, so call the local building department and ask before the crew is scheduled. The answer takes one phone call and saves an argument later.

If you live under a homeowners association, read the covenants before you pick a color or profile. Some specify both, and some restrict where downspouts can land.

Then think about the water itself. Downspouts that dump at the foundation undo the point of the system, and local stormwater rules may restrict where discharge can go. Ask each bidder where the water will end up and whether extensions, splash blocks, or a dry well are in the price.

What to Inspect When the Crew Finishes

Run water before you pay the balance. Put a hose at the far end of a run and watch the flow reach the outlet. Water should move steadily toward the downspout, with no flat spots holding a puddle.

Check that hangers are tight to the fascia along the whole run, that corners and outlet joints are sealed, and that downspouts are fastened at the top and bottom. Look behind the gutter for a gap where water can slip between metal and roof edge.

Walk the ground afterward with a magnet to pick up screws and metal slivers that flatten tires.

Your first step is small: walk the perimeter with a notepad, sketch each run, and count the existing downspouts. That sketch is what you hand each bidder, and it makes every proposal easier to compare.

Keep reading

Homeowners ask

How long do aluminum gutters last?

Trade sources put the working life at 20 years or more when the system is sized, sloped, and fastened correctly. Cleaning the gutters twice a year helps them get there.

Do I need a permit to replace gutters?

It depends on where you live, so call the local building department and ask before the crew is scheduled. Rules vary by city and county.

Is .032 aluminum worth the extra cost?

On long runs, two-story elevations, steep roofs, and anywhere ice sits in the trough, the thicker stock resists denting and sagging better. On short runs over a one-story roof with properly spaced hangers, .027 is a reasonable choice.

How many downspouts do I need?

Each square inch of downspout cross section drains about 100 square feet of watershed, so a 2-by-3-inch spout covers up to 600 square feet and a 3-by-4-inch spout covers 1,200. Going from one downspout to two doubles what a run of gutter can drain.